Pittsfield Town Hall Building Committee Meeting Minutes
Monday, November 7, 2022
Agenda
Minutes Approval: October 24, 2022
Public Present:
Old Business:
1. electrical Installation update
2. heat & duct decisions
New Business
Next Meeting Date: TBD
Adjournment:
Herb moved to call the meeting to order at 5:02pm. Glenn seconded. All in Favor.
Herb Kuendig, Mike Moran, Ray Colton, Glenn Reinauer, Jeremy Rayner, Richard Gaston in attendance.
Agenda Modification:
Minutes Approval: October 24 , 2022- Mike moved that the meeting minutes be accepted. Richard seconded. All in favor.
Public Present:
Old Business:
Next Steps:
b: installation of basement windows
c: re-siding & insulating southern and east exterior walls
Next Meeting Date: TBD
There being no further business of the committee, Jeremy moved to adjourn the meeting at 5:51pm. Glenn seconded. All in favor.
Recorded by:
s/Ann Kuendig
Approved: December 6, 2022
Herb Kuendig
Monday, November 7, 2022
Agenda
Minutes Approval: October 24, 2022
Public Present:
Old Business:
1. electrical Installation update
2. heat & duct decisions
New Business
- Next Steps
Next Meeting Date: TBD
Adjournment:
Herb moved to call the meeting to order at 5:02pm. Glenn seconded. All in Favor.
Herb Kuendig, Mike Moran, Ray Colton, Glenn Reinauer, Jeremy Rayner, Richard Gaston in attendance.
Agenda Modification:
Minutes Approval: October 24 , 2022- Mike moved that the meeting minutes be accepted. Richard seconded. All in favor.
Public Present:
Old Business:
- Electrical Installation: Dave McKinnon with 4 Security in Rutland who was hired by our contracted electrician to re-install the fire alarm system has started work. The electrician, Craig Petersen has not returned to the project and indicated he probably won’t. J-5 Electric-Mike Juris submitted an estimate for installing the subpanel and electrical in the walls which he could start in about a week and a half. He can work by the hour at $100 an hour and the job would take approximately two days. Estimated labor $1,600 and about the same for materials. Ceiling lighting is estimated to take two weeks. Members discussed reaching out to other master electricians for more estimates and availability. Herb will check with Fire Safety Inspector to see if Craig pulled a permit and if so, how to close it out.
- Heat & Duct Decisions: Member reviewed costs for two heat options: adding two propane heaters & eliminating furnace and need for duct work and new oil tank VS maintaining current furnace, installing limited duct work and new smaller fiberglass oil tank. Glenn moved to approve the second option. Jeremy seconded. All in favor.
Next Steps:
- Jeremy received a quote from woodworker Steve Fuchs to build a new custom front door out of mahogany not to exceed $3,500. Discussion on staining vs painting. Jeremy moved to accept the bid, Glenn seconded. All in favor. Funds for this project would be deducted from Town Hall Reserve Fund. Mike to coordinate with CV Oil on installation of duct work and gas hookups for stove and insta-hot water heater. Herb will call Charlie at CV Oil with go ahead for new tank. Ray will check with his electrician, Jeremy to check with Frank Candido. Ann was asked to prepare bids for the Town to put out for the following projects:
b: installation of basement windows
c: re-siding & insulating southern and east exterior walls
Next Meeting Date: TBD
There being no further business of the committee, Jeremy moved to adjourn the meeting at 5:51pm. Glenn seconded. All in favor.
Recorded by:
s/Ann Kuendig
Approved: December 6, 2022
Herb Kuendig